The Day 44 Problem: Alberta Courts Show No Mercy for Late Liens
Most lien disputes involve a contractor who left the paperwork until the last minute. A 2026 appeal decision of the Court of King's Bench shows how costly that can be, and why owners and contractors should treat lien timelines as a project management issue rather than a legal afterthought.
What happened
In The Micro Collective Inc v Hutterian Brethren Church of Tschetter, 2026 ABKB 547, Justice C. Magnan heard an appeal from Applications Judge J.T. Prowse, who had discharged two builders' liens on a greenhouse project. The claimants' agreements had been terminated in early March 2023. They sent their liens to the Calgary Land Titles P.O. Box, and the liens arrived on what turned out to be the last permitted day. A registrar did not enter them into the Pending Registration Queue until the next morning.
On appeal, the Court confirmed that, under the Land Titles Act, a statutory deadline is met when the document enters the Queue, not when it reaches the office. One day late was enough, and the liens ceased to exist. Like the Applications Judge below, the Court would not use its corrective powers to save the liens. Two levels of the Court have now reached the same result, which leaves little room for arguing otherwise.
There was a second trap. The contracts had been signed before the Prompt Payment and Construction Lien Act took effect, so the old 45-day limit applied, not the current 60 days. Remember to be mindful of whether your contract is governed by Alberta's former Builders' Lien Act or the Prompt Payment and Construction Lien Act.
The other side of the coin
Owners should not assume the Queue only works against lien claimants. In CCS Contracting Ltd v Condominium Corporation No 1520090, 2023 ABKB 147, the Court held that the 180-day period to sue and register a certificate of lis pendens starts only once the lien actually appears on title. When Land Titles is backlogged, an owner may wait months before that clock starts. In practical terms, other steps that depend on the registration date may be pushed back as well. These include serving a notice to commence action, releasing holdback or posted lien funds, and clearing title for a financing or sale.
What you should do
Contractors and subcontractors:
- Track your last day of work on every job as it happens.
- Confirm which statute governs each contract. Two contracts on the same site can have different deadlines.
- Submit well before the deadline, and don't plan around mail or courier timing.
Owners and lenders:
- Monitor title for Queue submissions as well as registered instruments.
- Expect holdback and lien security to stay outstanding longer than the statute suggests on paper.
- Before treating a lien as lapsed, confirm when it was actually registered.
The common thread is simple: the courts will enforce these deadlines strictly. Planning early costs far less than litigating late.